The Móra d’Ebre City Council has initially approved and submitted for public review the project for a themed children’s leisure area at the Illa de Saurí, with a total execution budget of 294,897.91 euros (VAT included). The agreement was adopted by the Local Government Board in a session on October 5, 2026, and was published in the Official Gazette of the Province of Tarragona on October 16, 2026, with the official reference CVE 2026-09510. The document is signed by the mayor-president, Rubén Miquel Biarnés Renedo, with a signature date of October 9, 2026.
This is a municipal works project that is now entering the processing phase prior to its final approval. The approved text is titled “Project for a themed children’s leisure area at the Illa de Saurí, in Móra d’Ebre, TM Móra d’Ebre” and was drafted by the Civil Engineer Alejandro Lerma Gómez.
A facility of nearly 295,000 euros
The total execution budget of the project is 294,897.91 euros, including VAT, as stated in the announcement published in the provincial gazette. The figure corresponds to the complete execution of the themed children’s leisure area planned for the Illa de Saurí, a river space in the Ribera d’Ebre municipality.
The technical and administrative elements included in the announcement are as follows:
- Official designation: “Project for a themed children’s leisure area at the Illa de Saurí, in Móra d’Ebre, TM Móra d’Ebre”.
- Promoter: Móra d’Ebre City Council.
- Drafter: Alejandro Lerma Gómez, Civil Engineer.
- Total execution budget: 294,897.91 euros, VAT included.
- Approving body: Local Government Board, in a session on October 5, 2026.
- Official announcement reference: CVE 2026-09510.
Thirty business days to consult and object
The file is available to any interested person at the municipal offices, every business day during office hours. The consultation period is thirty business days starting from the last publication of the announcement, whether in the BOPT or on the electronic notice board of the Móra d’Ebre City Council.
During this same period, any objections deemed relevant may be formalized before the City Council. The announcement does not detail any other specific submission channel, meaning the usual registries of the convening local administration apply.
Effects of the initial agreement
The publication corresponds to an initial approval, not a final one. If no objections or claims are presented once the deadline has expired, the initial agreement will automatically become final, as indicated in the announcement itself.
This mechanism is standard in the processing of municipal investments: public information opens the door to neighborhood or technical amendments before the project is finalized and can proceed to tender and execution.
The news is of direct interest to the residents of Móra d’Ebre, who will gain a public-use children’s leisure facility, and to companies in the public works sector that may compete for the future contract. The schedule will depend on the result of the objections process and the subsequent final approval of the project.
Source: Official Gazette of the Province of Tarragona, no. 16-10-2026, Local Administration, p. 1-1 (official reference: CVE 2026-09510).