The Government Delegation rectifies the estates of the Cardoso-Reboria line

Por FactBox Admin

La Delegación del Gobierno rectifica las fincas de la línea Cardoso-Reboria

The Government Delegation in Asturias has rectified the list of assets and rights for the project of the new 400 kV overhead electric power transmission line Cardoso-Reboria, after noting that the initially published list omitted the affected properties in the municipal districts of Gijón and Corvera de Asturias. The correction is published in the Official Gazette of the Principality of Asturias (BOPA) number 217, dated November 10, 2026, section III-State Administration, with the reference Code 2026-09023. The announcement reproduces in full the list of plots from file 85-G/2026, promoted by Red Eléctrica de España, S. A. U.

The project, titled “New 400 kV overhead electric power transmission line, double circuit, SE Cardoso-SE Reboria,” runs through the councils of Carreño, Corvera de Asturias, and Gijón and aims to improve the security of supply in the central area of Asturias. According to the technical characteristics released during the processing, the line is 10.843 kilometers long, with two circuits, three conductors per phase, metal lattice tower supports, and a thermal transport capacity of 2,180 MVA per circuit in summer and 2,400 MVA in winter. The project budget amounts to 8,381,937.86 euros.

The action appears as “Gozón-Reboria 400 kV Line” in the 2021-2026 Energy Planning, approved by Agreement of the Council of Ministers on March 22, 2022, and published by Resolution of the Secretary of State for Energy on April 8, 2022, in the Official State Gazette number 93, dated April 19, 2022. The resolution of the authorizations corresponds to the General Directorate of Energy Policy and Mines of the Ministry for the Ecological Transition and the Demographic Challenge, while the processing of the file corresponds to the Industry and Energy Area of the Government Delegation in Asturias, and the environmental impact statement to the General Directorate of Environmental Quality and Assessment.

Three publications and a material error

The original public information announcement was published on October 13, 2026, in BOPA number 197, with the reference Code 2026 08097 and eight pages. On October 26, 2026, BOPA number 207 (Code 2026 08455) included a first rectification, limited to correcting the malfunction of the download links for the environmental impact study and the project.

Now, the body explains that “a material error” has been noted in the list of assets and rights: the absence of the affected properties in Gijón and Corvera de Asturias. Therefore, it republishes the complete list, signed in Oviedo on October 29, 2026, by the Director of the Industry and Energy Area. The document specifies that “official bodies are included for informational purposes.”

What the new list contains

The table identifies each plot by project number, owner, cadastral reference, polygon, plot, flight easement area, security zone, temporary occupation, access, supports and ground ring, right of way, nature of the land, and existing easements.

  • Carreño: the list goes up to plot number 107, with cadastral references from polygon 39 and earlier, and supports such as T-1, T-11, T-17, or T-18.
  • Gijón: plots with cadastral references from polygons 24, 26, and 29 (series 52024A024, 52024A026, and 52024A029) and supports T-18, T-19, T-20, and T-25, among others.
  • Corvera de Asturias: 18 plots with references from polygons 23 and 27 (series 33020A023 and 33020A027) and supports T-12, T-13, T-14, and T-15.
  • Land: eucalyptus groves, timber pine forests, meadows, pastures, and scrubland predominate, along with unproductive areas and public domain communication routes.

Public owners, companies, and heirs

Among the holders are administrations and public entities such as the Gijón City Council, the Carreño City Council, the Principality of Asturias, the Consortium for Solid Waste Management in Asturias, the Ministry of Transport, Mobility and Urban Agenda, and the Cantabrian Hydrographic Confederation, O. A.

The list of affected companies includes Casona Parque XXI, S. L., Rubiera Predisa, S. L., Alkea Eco, Contratas Mota, S. A., Grupo Loarte Real Estate, S. L., Glatfelter Sontara Asturias, S. A. U., and the Animal Protection Foundation of the Principality of Asturias. The remaining plots belong to private individuals, many of whom are identified as heirs—González-Posada González, González Sánchez, Menéndez Bernardo, or Pérez Barrios, among others—and several appear under the name “Unknown.”

The relevance of the announcement is direct for the owners: the declaration of public utility of the project makes this list the official reference for the occupation and easements of their land, and the inclusion of the estates in Gijón and Corvera de Asturias allows their holders to be included in the procedure. The announcement of October 13 opened a thirty-day period for allegations starting from the day following its publication, which could be submitted to the Electronic Registry of the General State Administration or any of the registries listed in Article 16 of Law 39/2015.


Source: Official Gazette of the Principality of Asturias, no. 217, of November 10, 2026, section III-State Administration, page 1 (official reference: Code 2026-09023).