Justice tenders the new Courthouse building in Talavera for 13.8 million

Por FactBox Admin

Justicia licita por 13,8 millones el nuevo edificio de Juzgados de Talavera

The Ministry of the Presidency, Justice and Relations with the Courts has put out to tender the works for the new Courthouse building in Talavera de la Reina (Toledo), with an estimated value of 13,836,522.01 euros and an execution period of 46 months. The tender announcement, processed by the Secretary of State for Justice under file AOB/2026/021, is published in the Official State Gazette (BOE) no. 249, dated October 7, 2026 (reference BOE-B-2026-32493). Interested companies may submit their bids until 2:00 PM on November 3, 2026.

The contract will be awarded through an open procedure and will not admit variants. The contracting authority is the Secretary of State for Justice, with NIF S2813610I and headquarters at calle San Bernardo 21 in Madrid, and the declared main activity is the provision of general public services. The announcement was sent to the Official Journal of the European Union on October 1, 2026, with identifier 2026-000602781, and the submission date of the announcement itself is also October 1, 2026. The document is signed by the Secretary of State for Justice, Manuel Olmedo Palacios.

A construction contract of nearly 14 million and 46 months

The tender refers to the construction works of the new judicial building, classified under CPV code 45213150 (construction work for office buildings). The main location of the works corresponds to NUTS code ES300, and the estimated value of the contract amounts to 13,836,522.01 euros.

The planned duration of the contract is 46 months. The procurement specifications are available for free, direct, and complete access through the buyer profile of the State Procurement Platform.

Award criteria and bid conditions

The evaluation of proposals will be divided among three criteria:

  • Price: weighting of 45%.
  • Value judgments: weighting of 35%.
  • Improvement of the warranty period, as an automatic criterion: weighting of 20%.

Regarding participation conditions, capacity to act, compliance with Social Security obligations and tax obligations are required, and for foreign companies, a declaration of submission to Spanish legislation. Annual turnover and previously completed works will also be evaluated.

The execution incorporates environmental considerations: documentation must be submitted in electronic format and, if submitted on paper, it must be 100% recycled; furthermore, communications between the contractor and the Administration will be carried out by electronic means. Electronic submission of bids, electronic invoicing, and electronic payment will be accepted, and bids must be written in Spanish.

Deadlines, opening, and appeal process

The procedure schedule is established as follows:

  • Submission of bids: until 2:00 PM on November 3, 2026.
  • Opening of the economic bid envelope: November 18, 2026, at 10:00 AM, estimated date, at the headquarters of the Ministry of the Presidency, Justice and Relations with the Courts (San Bernardo 21, Madrid).
  • Mandatory bid maintenance period for the bidder: 15 days.
  • Competent body for appeals: Central Administrative Tribunal for Contractual Appeals, located at Avenida General Perón 38, Madrid.

Background: from project to construction

This tender gives continuity to the previous work of project drafting and construction management for the same building, processed by the Contracting Board of the Ministry of Justice under file ASE/2022/074. That contract, with an estimated value of 853,270.88 euros and a duration of 30 months, was published in the Official State Gazette (Boletín Oficial del Estado) no. 168, of July 14, 2022 (reference BOE-B-2022-22832).

The formalization was announced in the Official State Gazette no. 105, of May 3, 2023 (reference BOE-B-2023-12807), after receiving 9 bids and with an award date of March 1, 2023. The joint venture of GIRA ARQUITECTOS S.L.P. and JAVIER FUSTER ARQUITECTOS SLP was awarded the contract for an amount of 535,000.00 euros.

The tender now published represents the transition from the project phase to the material execution of a judicial facility long demanded in the region, with a public investment exceeding 13.8 million euros and a construction horizon of nearly four years. The new courthouse building in Talavera de la Reina will concentrate the city’s judicial bodies in a modern headquarters, with the consequent impact on the public Justice service and on the economic and labor activity of the surroundings during the construction phase.