BOP de Huesca · 01 Oct 2026 · 19 vistas
Public information on the addendum for the 220 kV Mangraners-Peñalba line
Por FactBox Admin

The Industry and Energy Area of the Government Sub-delegation in Huesca has submitted for public review the addendum to the project for the overhead-underground electric power transmission line at 220 kV with a double circuit between the Mangraners and Peñalba substations. The announcement is published in the Official Gazette of the Province of Huesca number 188, corresponding to Thursday, October 1, 2026, with reference BOPH-2026-188033 and file 4321, and opens a period of 30 business days to submit allegations. The modification affects landowners in Fraga, Candasnos, and Peñalba, in the province of Huesca.
The procedure jointly covers the request for the Environmental Impact Statement, Prior Administrative Authorization, Administrative Construction Authorization, and Declaration, specifically, of Public Utility. The petitioner is Red Eléctrica de España, Sociedad Anónima Unipersonal, with registered office at Paseo del Conde de los Gaitanes 177, La Moraleja, Alcobendas (28109 Madrid).
The competent substantive body to resolve is the General Directorate of Energy Policy and Mines of the Ministry for the Ecological Transition and the Demographic Challenge, which is also the environmental body responsible for issuing the Environmental Impact Statement. The processing complies with Title IX of Law 24/2013, of December 26, on the Electricity Sector, Royal Decree 1955/2000, of December 1, and articles 36 and 37 of Law 21/2013, of December 9, on Environmental Assessment. The addendum responds to allegations from affected individuals and reports issued during the public information process of the original project, whose budget amounted to 35,732,014 euros; the budget for the addendum is estimated at 17,594,846 euros.
Overhead route variants and underground changes
The addendum incorporates specific modifications to the original project. In the underground section of Lleida, splice chambers CE01, CE02, CE03, and CE04 are moved off the roadway to a green area inside the sidewalk, and the trench between CE03 and CE04 is moved to the west sidewalk. Four variants are defined for the overhead route:
- Variant No. 1: between supports T-13 and T-15, with 3 supports and 0.731 km, in Albatàrrec.
- Variant No. 2: between T-21 and T-24, with 4 supports and 1.304 km, in Montoliu de Lleida and Sudanell.
- Variant No. 3: between T-103 and T-107, with 7 supports and 1.895 km, in Fraga.
- Variant No. 4: between T-145 and T-149, with 6 supports and 1.984 km, in Candasnos and Peñalba.
Technical characteristics of the installation
The projected line maintains two circuits and a maximum conductor operating temperature of 85 ºC, with a thermal transport capacity of 720 MVA per circuit in summer and 860 MVA in winter. The conductor is of the AL/AW TERN type and the supports are metal lattice towers.
- Total length of the overhead section: 72 km in the addendum, compared to the 71.835 km of the original project.
- Underground section: 484.83 MVA per circuit, 4 splice chambers, and 24 splices.
- Length of the underground line: 3 km in circuit 1 and 3.1 km in circuit 2, within the municipality of Lleida.
Affected Parties and Period for Allegations
The municipalities affected by the addendum subject to public information are Fraga, Candasnos, and Peñalba, in the province of Huesca, and Lleida, Albatàrrec, Montoliu de Lleida, and Sudanell, in the province of Lleida. In the Huesca section, the affected owners include, among others:
- Fraga City Council, Peñalba City Council, Candasnos City Council, and the General Deputation of Aragon.
- Red Eléctrica de España, S.A.U., Frutas Aurelio, S.L.U., Jorge Gros Clavel, Luis Ángel Gros Clavel, Eva Gros Clavel, Antonia Elena Badia Zapater, Elena Catalán Badia, Laura Catalán Badia, Elisa Catalán Badia, Jorge Sánchez Noguero, Marcial Llusà Labrador, Víctor Llusà Labrador, Maria Teresa Saló Costa, Francisca Larroya Achón, and Agustín Sarrau Morell.
- Ramón Labara Ballestar, Manuel Andrés Mateo Ballestar, Lourdes Mateo Ballestar, Ángel Guallarte Aguilar (heirs), Víctor Hugo del Pueyo Meler, María Arantzazu del Pueyo Meler, Beatriz del Pueyo Meler, and Jesús Ezquerra Cacho.
The project and the parcel maps may be examined at the Industry and Energy Area of the Government Sub-delegation in Huesca (Plaza Cervantes 1, Huesca) and at the Industry and Energy Department of the Government Sub-delegation in Lleida (Plaza de la Pau 1, Lleida), as well as via the link from the Ministry for the Ecological Transition and the Demographic Challenge. Allegations shall be submitted within a period of 30 business days starting from the day following the publication of the announcement, in writing at the General Registry of the Government Sub-delegation, through the electronic registry of the General State Administration, or by the means provided for in Article 16 of Law 39/2015, of October 1. Legal entities and entities without legal personality are required to communicate by electronic means.
The Declaration, specifically, of Public Utility implies the need for the occupation of assets and urgent occupation for the purposes of Article 52 of the Law of December 16, 1954, on Compulsory Expropriation. The announcement was signed in Huesca on September 10, 2026, by the Director of the Industry and Energy Area, René Gómez López de Munain.
The publication opens the final window for owners of the affected plots to file objections against the new layouts before the authorizations and the declaration of public utility—which enables the urgent expropriation of the land—are resolved.
Source: Official Gazette of the Province of Huesca, No. 188, October 1, 2026, State Administration, p. 64 (official reference: BOPH-2026-188033).