La Parra and La Morera estates, expropriated for the power line
Por FactBox Admin

The Regional Government of Extremadura (Junta de Extremadura) has summoned the owners of the estates affected by the project to replace the medium-voltage overhead line (LAMT) between supports A344576 and A431654, in the municipal districts of La Parra and La Morera, for the drawing up of records prior to occupation. The summons is published in the Official Gazette of the Province of Badajoz No. 197, dated October 14, 2026, via Announcement 3850/2026. The appearances will take place on November 4 and 5, 2026, at the town halls of both localities.
The announcement comes from the Industrial, Energy and Mining Planning Service, under the General Directorate of Industry, Energy and Mines of the Ministry of Industry, Energy, Science and Territory. On February 12, 2026, a resolution was issued authorizing the construction of the project and specifically declaring it to be of public utility, following the corresponding public information process. This declaration, in accordance with Article 54 of Law 24/2013, of December 26, on the Electricity Sector, implies the necessity of occupying the affected assets and rights and entails urgent occupation for the purposes of Article 52 of the Compulsory Expropriation Law, of December 16, 1954.
In the expropriation file, Edistribución Redes Digitales, SLU assumes the status of beneficiary. The files are 06AT-1788-18000 and BA-EXF:3/2026, although Annex I lists them as 06AT-1788/18000 and BA-EXF: 2/2026. The publication also serves as notification to unknown owners or those whose address is unknown, according to Article 44 of Law 39/2015, of October 1, on the common administrative procedure.
Two days of appearance
The drawing up of prior records will be held at the town halls of the affected municipalities, on the day and time listed in Annex I of the announcement. The schedule is also posted on the notice boards of the town halls and will be communicated to each interested party via a summons notification.
- November 4, 2026: appearances in La Parra, between 9:40 and 12:45 hours.
- November 5, 2026: appearances in La Morera, between 10:10 and 11:45 hours.
Interested parties, as well as those who hold any type of rights and interests over the affected assets, must attend personally or be represented by a duly authorized person, providing documents proving their ownership and the most recent receipt of the Real Estate Tax (IBI). They may be accompanied, at their own expense, by their experts and a notary if they deem it appropriate.
Owners summoned on November 4 in La Parra
- Seticel y Servicios, SL (Carretera Morera area), at 9:40.
- José Luis Nieto Gutiérrez and Isabel Pizarro Marabel (Moralito area), at 10:10.
- Ángel González Sanabria, José María González Galindo, Antonia González Galindo and Ángel González Galindo (Retama area, dryland olive grove), at 10:40.
- Luis Carlos Carretero Fernández and Máximo González Almeda (Llanazo area), at 11:15.
- Francisco Carretero Pérez (La Correra area, support AP-6), at 11:30.
- Mateo Barbosa Corbacho and Antonia Gutiérrez Santos (Cortesía area, support AP-17), at 11:45.
- Antonia Gutiérrez Santos, Cándida Gutiérrez Santos and Mateo Barbosa Corbacho (Cortesía area), at 12:15.
- Francisco Barbosa Contreras (Cortesía area), at 12:45.
Owners summoned on November 5 in La Morera
- Lorenzo Manuel Álvarez Vera and the heirs of Juan Francisco Álvarez Vera (Fontanilla area), at 10:10.
- Ascensión Nieto Flores (Fontanilla area, support AP-25), at 10:40.
- Francisco Flores Nieto, Alicia Gutiérrez Flores and Policarpo Flores Nieto (Fontanilla area), at 11:10.
- Francisco Amo Meléndez (Fontanilla area), at 11:45.
Impacts on the land
The annex details for each plot the cadastral reference, the polygon and the plot, the flight meters, the square meters of right-of-way easement, the number of supports, full ownership, and temporary occupation, as well as the land use. Uses include dryland farming, dryland olive grove, unproductive, and industrial.
The impacts include flights of up to 133.53 meters and right-of-way easements of up to 1,853.54 square meters, with temporary occupations reaching 185.35 square meters. The announcement is signed by the Head of the Industrial, Energy and Mining Planning Service, Juan Francisco Lemus Prieto.
The summons opens the expropriation phase of a project affecting about twenty owners in La Parra and La Morera, whose lands are subject to right-of-way easements and temporary occupation for the installation of the new line. The holders must appear on the fixed dates to determine the value of the affected assets and rights, providing documentation that proves their ownership.
Source: Official Gazette of the Province of Badajoz, no. 197, October 14, 2026, Regional Administration, pgs. 2-5 (official reference: Announcement 3850/2026).