Energía expands the public utility of Naturgy's El Tabaibal wind farm
Por FactBox Admin

The General Directorate of Energy of the Government of the Canary Islands has granted Naturgy Renovables Canarias, S.L.U. the modification of the declaration, specifically, of public utility for the project called El Tabaibal Wind Farm, 4.7 MW, in the municipal districts of Santa Lucía de Tirajana and Agüimes, on the island of Gran Canaria. The resolution of the Director General of Energy is dated September 4, 2026, and is published in the Official Gazette of the Province of Las Palmas number 120, of October 7, 2026, on page 17115, with announcement number 3,190 and file number ER150053. The declaration of public utility is the legal requirement that enables the compulsory expropriation of the assets and rights necessary to execute the installation.
The announcement is disseminated in compliance with the provisions of Article 21 of the Law of December 16, 1954, on compulsory expropriation, a regulation that requires the publication of resolutions of this nature for the knowledge of the affected owners. The competent body is the General Directorate of Energy, under the Ministry of Ecological Transition and Energy of the Government of the Canary Islands, which acts as the authorizing administration regarding electrical energy production installations from renewable sources in the archipelago.
A modification of the original 2024 declaration
The resolution now published modifies the declaration of public utility that the management center itself had granted through resolution number 861/2024, of July 25, 2024. The wind farm already had, therefore, the recognition of public utility since the summer of 2024, and the new pronouncement updates that recognition for the 4.7 MW project promoted by the energy group’s Canarian subsidiary.
The official text does not detail the estates or the specific owners affected in the announcement, which are identified in the full content of the resolution.
File and project data
- Promoter: Naturgy Renovables Canarias, S.L.U.
- Installation: El Tabaibal Wind Farm, 4.7 MW
- Location: municipal districts of Santa Lucía de Tirajana and Agüimes, island of Gran Canaria
- Resolving body: General Directorate of Energy (Ministry of Ecological Transition and Energy, Government of the Canary Islands)
- Date of resolution: September 4, 2026
- Precedent: resolution number 861/2024, of July 25, 2024
- File: ER150053
- Publication: Official Gazette of the Province of Las Palmas number 120, of October 7, 2026, p. 17115
Consultation of the resolution and signature of the announcement
The full content of the resolution is available on the official page of the General Directorate of Energy of the Ministry of Ecological Transition and Energy, accessible via the link enabled on the electronic office of the Government of the Canary Islands.
The announcement appears signed in Las Palmas de Gran Canaria on September 7, 2026, by Alberto M. Blasco Lorenzo, head of the Energy Technical Area, acting by delegation of the Director General of Energy in accordance with Resolution Number 462/2026, of March 20, 2026.
The publication opens the way for the owners of the affected lands to learn the scope of the action and, where appropriate, be summoned to the expropriation proceedings, while consolidating the deployment of wind energy in the southeast of Gran Canaria, one of the areas with the highest concentration of renewable projects in the islands.
Source: Official Gazette of the Province of Las Palmas, number 120, October 7, 2026, section II (Administration of the Autonomous Community), page 17115 (official reference: announcement 3.190, file ER150053).