Aerothermal energy: Sant Joan de Vilatorrada will replace the gas boiler

Por FactBox Admin

The City Council of Sant Joan de Vilatorrada has submitted to public information the executive project to replace the gas boiler with an aerothermal heat pump, with a base tender budget of €715,495.18, VAT included. The notice, initially approved by the Plenary of the Corporation on May 28, 2026, is published in the Official Gazette of the Province of Barcelona (BOPB) of August 4, 2026, with the official reference CVE 202610127526. Interested parties have 30 business days to review the file and submit allegations.

The project —“Executive project for an aerothermal heat pump to replace the gas boiler and other installations in the production of heating and cooling at the City Council of Sant Joan de Vilatorrada”— is covered by articles 36 to 38 of the ROAS (Regulations on works, activities and services of local bodies), which regulate public information for municipal works projects. The document received initial approval from the Plenary of the Corporation on May 28, 2026, and is now placed on public display before its final approval.

Key project figures

  • Base tender budget (excluding VAT): €591,318.33
  • VAT: €124,176.85
  • Total: €715,495.18
  • Initial approval: Plenary of the Corporation, May 28, 2026
  • Official reference: CVE 202610127526

A commitment to aerothermal energy in municipal facilities

The action entails abandoning a fossil fuel source, the gas boiler, and installing an aerothermal heat pump, a renewable technology that harnesses the energy from outdoor air to produce heating and also cooling. With this change, the council takes a step forward in the energy transition of its facilities and eliminates gas consumption in the production of heating and cooling for the municipal building stock.

30-business-day period for allegations

In accordance with the ROAS, the notice has been published in the BOPB, in one of the most widely circulated newspapers in the province, and on the City Council’s notice board. The period for submitting allegations and suggestions is 30 business days, counted from the last publication.

How to consult the file and file allegations

During the public information period, interested parties may consult the project and submit allegations:

  • Consultation point: electronic notice board of the City Council (https://www.santjoanvilatorrada.cat/ca/seu-electronica/tauler-danuncis)
  • Deadline: 30 business days from the last publication of the notice
  • Recipients: any person interested in or affected by the project
  • Effect: if no allegations or suggestions are submitted, the project becomes finally approved

The announcement, signed on 23 July 2026 by the mayor, Jordi Solernou Vilalta, stresses that, once the deadline has passed without objections or suggestions, the project will be definitively approved. Publication in the official gazette thus opens the final phase of participation before the action is consolidated.

With an estimated investment of more than €715,000, Sant Joan de Vilatorrada is taking a major step towards electrifying and decarbonising the heating and cooling systems of its municipal facilities. Citizens and businesses now have the opportunity to review the project and make contributions before it becomes final.